More capacity

Requesting additional capacity

Whether you are expanding your facility, need additional capacity at a grid connection point or require incremental capacity within the European market area network, here you will find the right type of request for your needs.

KARLA Gas 2.0:
Reserving capacity

Reserving transport capacity

You can reserve transport capacity in our transmission network if you are

  • an industrial customer,
  • an operator of storage, LNG or production facilities, or
  • an operator of gas-fired power plants that are to be connected to a transmission network.

You can also increase your existing connection capacity if your facilities are to be expanded.

Requirements for reservation

In accordance with operative provision 8 of the KARLA Gas 2.0 determination, operators must meet certain requirements and provide OGE with evidence of:

  • A brief description of the facility concept or the expansion measures
  • A brief summary of the current status of the permitting procedure
  • The date of the first gas offtake

How the reservation works

Once we have received your complete documents, we will review your request within two months. If the reservation is possible, we will secure the required capacity in the network for you.

Reservation fee: A fee of 20% of the entry/exit tariff applicable at the relevant entry or exit point at the time the reservation agreement is concluded is charged. This fee is offset against a subsequent firm booking.

Important: The capacity reservation expires if the entry or exit point has not been firmly booked within three years of the transmission system operator receiving the reservation declaration.

Speeding up requests

To process your request under operative provision 8 of the KARLA Gas 2.0 determination as quickly as possible, we offer our connected parties a form for efficient handling. This gives us all the relevant information at a glance so we can process your request quickly.

Form / pdf / 153.05 KB

Reservation request

Open Grid Europe offers its shippers a form for the efficient handling of enquiries pursuant to clause 8 of the determination KARLA Gas 2.0. The use of the form is intended to ensure that Open Grid …Europe promptly obtains all information required to process your enquiry efficiently.

Individual assessment:
Requesting additional firm capacity

Do you currently lack, or expect to lack, firm capacity at a grid connection point to a final consumer? As a transport customer, we will be happy to check whether we can provide you with additional firm capacity.

To do so, apply for a binding individual assessment using the form provided here.

Process and deadlines

We regularly assess additional demand once a year. If you send us your request by 15 July of a given year, you will receive a binding response by 15 October. However, we can often also assess additional demand during the year and confirm it at short notice. Feel free to contact us at any time.

Important note

Your request for a individual assessment is also a binding booking request. If we can provide the requested additional capacity, the resulting offer is binding for you. Further information can be found in our network access conditions and in the form.

Form / pdf / 81.33 KB

Request for an individual assessment

We could not book firm capacities in line with an online-request / booking via PRISMA. Therefore, we request – with reference to Section 2 of Appendix 2 of the „General Terms & Conditions for the …Entry/Exit Contracts (entry/exit system) as amended from time to time (hereinafter called „General Terms & Conditions“) – a binding individual capacity assessment including the following data

Incremental capacity:
Process for new capacity

In accordance with Chapter V of Regulation (EU) 2017/459 [NC CAM], the German transmission system operators carry out a process to determine the demand for incremental capacity. The process starts in odd-numbered years after the annual auction and lasts two years.

General information

All information on past and ongoing incremental capacity processes is available on the dedicated FNB Gas website.

Publication pursuant to Art. 28(3) NC CAM

For the ongoing incremental capacity process between the BeLux market area (ZTP) and the German market area (THE), the transmission system operators involved have made the required publications pursuant to Art. 28(3) NC CAM. The relevant information can be viewed here.

Go to the publications pursuant to Art. 28(3) NC CAM

Fees pursuant to Art. 26(11) of Regulation (EU) 2017/459 [NC CAM]

From the 2023–2025 incremental capacity cycle onwards, the transmission system operators charge a fee pursuant to Art. 26(11) of Regulation (EU) 2017/459 [NC CAM] for their activities related to the submission of non-binding demand indications. The fee is €30,000 per market area border, request type (new capacity or capacity to be upgraded) and flow direction.

Please note that the fee will also be charged if the non-binding demand indication is submitted to the German transmission system operators not by the requesting party itself but by a third party, for example an adjacent foreign transmission system operator (cf. para. 37 BK9-22/042).

The approval by the Bundesnetzagentur and further information can be found in decision BK9-22/042.

Go to decision BK9-22/042